Northern Minerals Browns Range Project&Financing Update

October 12, 2017      Source:Northern Minerals

Keywords:rare earth

Northern Minerals Limited is pleased to provide an update with regards to financing and construction progress for the Browns Range Heavy Rare Earths Project in the East Kimberley, WA.


Brown Range Construction Update

At site, MACA Limited has completed the bulk earthworks ahead of process pilot plant concrete works and the first deliveries of the modular processing plant components in early November.

Primero has commenced establishment of its team and equipment on site to undertake concrete works ahead of the process pilot plant delivery.

MACA is continuing with mining at Gambit West and Wolverine. With both pits expected to be completed before the end of 2017.Ore is being stockpiled on the ROM pad for the three-year processing pilot project.

Fabrication update

Sinosteel MEXX has completed the first modules of the Browns Range processing plant and has prepared them for transport to Australia. The first components are currently in Shanghai awaiting shipment by the end of the week.

The remaining processing plant components are on track for completion and delivery to site in early 2018. The timetable for first mixed rare earth carbonate production by mid-2018 remains on track.


2009 Copyright & ruidow.com, Inc. All Rights Reserved. all rights reserved. Beijing ICP Certificate No. 09060886

Address: Room 1608, No. 2 Pumanshan Building, No. 71 Songzhuang Road, Fengtai District, Beijing, China zip code: 100079

Tel: 86 10 87653120 Fax: 86 10 87653110 E-mail: beth@Ruidow.com